CATU and ARATU

Customer: TAG – TRANSPORTADORA ASSOCIADA DE GÁS S.A.

Objective: Supply of materials, equipment and services, referring to the construction and assembly for implementation of the Gas Distribution Stations (GDS) of Catu and Aratu, in the state of Bahia.

Duration: 539 days (concluded in October 2010)

Total Man Hours: 1,180,000

Main quantities:

14” and 18” Gas Pipeline 12,200 m
Aerial Pipeline 8,200 m
Electrical Ducts 7,500 m
Power and control cables 29,900 m