Customer: PETROBRAS / ENGINEERING / IEABAST / IERL
Objective: Execution of civil construction, electromechanical assembly, conditioning, testing and guided operation services, including supply of materials for the Steam Portfolio Off-Site of the Landulpho Alves Refinery – RLAM, in São Francisco do Conde, state of Bahia.
Duration: 894 days (concluded in October 2010)
Total Man Hours: 1,854,300
Main quantities:
Continuous Helical Pile | 2,950 m |
Structural Concrete | 1,360 m³ |
Modules (structure and pipeline) | 354,500 Kg |
Metallic Structure | 263,000 Kg |
Pipeline | 185,000 Kg |
Valves | 570 units |
Instruments | 257 units |
Electrical Ducts | 9,300 m |
Power and control cables | 20,600 m |