Firefighting System Unit (COMPERJ)

Customer: PETROBRAS / ENGINEERING / IECOMPERJ

 Objective: Provision of services referring to the elaboration of the executive project, supply of equipment and materials, civil construction, electromechanical assembly and commissioning (preservation, conditioning, pre-operation, startup and guided operation) of the Firefighting System Unit, for the Rio de Janeiro Petrochemical Complex (COMPERJ).

 Duration: 1342 days (concluded in January 2016)

Total Man Hours: 2,690,000

Main quantities:

Excavation 72,600 m³
Structural Concrete 8,100 m³
Metallic Structure 250,000 Kg
Pipeline 4,457,000 Kg
Valves 2,150 un
Tank Ø 53m 720,000 Kg
Electrical Ducts 3,500 m
Power and control cables 52,300 m
Pumps 900m³/h 5 units